Quarterly report [Sections 13 or 15(d)]

REIMBURSABLE PUBLIC IMPROVEMENTS AND NOTE RECEIVABLE FROM THE SKY RANCH COMMUNITY AUTHORITY BOARD

v3.25.1
REIMBURSABLE PUBLIC IMPROVEMENTS AND NOTE RECEIVABLE FROM THE SKY RANCH COMMUNITY AUTHORITY BOARD
6 Months Ended
Feb. 28, 2025
REIMBURSABLE PUBLIC IMPROVEMENTS AND NOTE RECEIVABLE FROM THE SKY RANCH COMMUNITY AUTHORITY BOARD  
REIMBURSABLE PUBLIC IMPROVEMENTS AND NOTE RECEIVABLE FROM THE SKY RANCH COMMUNITY AUTHORITY BOARD

NOTE 2 – REIMBURSABLE PUBLIC IMPROVEMENTS AND NOTE RECEIVABLE FROM THE SKY RANCH COMMUNITY AUTHORITY BOARD

The Sky Ranch Community Authority Board (“Sky Ranch CAB”) and the Company’s agreements with the Sky Ranch CAB are described in greater detail in Notes 5 and 15 to the 2024 Annual Report.

The notes receivable – related party, reimbursable public improvements and project management fees are due to the Company from the Sky Ranch CAB and reports the balances owed by the Sky Ranch CAB to the Company for public improvements paid for by Pure Cycle which are reimbursable from the Sky Ranch CAB and include project management fees related to the Company’s management of the construction of the public improvements, and interest accrued on the unpaid balances related to the ongoing development of the Sky Ranch master planned community (Sky Ranch). Pure Cycle has advanced funds to the Sky Ranch CAB for the cost of constructing certain public improvements at Sky Ranch which are the ultimate responsibility of the Sky Ranch CAB. During the three and six months ended February 28, 2025, Pure Cycle spent $2.4 million and $6.5 million on public improvements which are payable by the Sky Ranch CAB to Pure Cycle. Since Pure Cycle believes the amounts are probable of collection, they have been added to the note receivable from the Sky Ranch CAB. Additionally, for the three and six months ended February 28, 2025, project management fees of $0.1 million and $0.4 million and interest income on the outstanding note receivable of $0.3 million and $0.8 million were also added to the note receivable. During the three and six months ended February 28, 2025, the Sky Ranch CAB paid Pure Cycle $0.4 million and $10.6 million pursuant to the note. Pursuant to the agreements with the Sky Ranch CAB, any payments received are initially applied to interest.  

During the three and six months ended February 29, 2024, Pure Cycle spent $1.0 million and $3.5 million on public improvements which are payable by the Sky Ranch CAB to Pure Cycle. Since Pure Cycle believes the amounts are probable of collection, they have been added to the note receivable from the Sky Ranch CAB. Additionally, for the three and six months ended February 29, 2024, project management fees of less than $0.1 million and $0.1 million and interest income on the outstanding note receivable of $0.2 million and $0.9 million were also added to the note receivable. During the three and six months ended February 29, 2024, the Sky Ranch CAB paid Pure Cycle $0.3 million and $0.3 million, respectively, pursuant to the note. Pursuant to the agreements with the Sky Ranch CAB, any payments received are initially applied to interest.  

The following table summarizes the activity and balances associated with the note receivable from the Sky Ranch CAB:

Three Months Ended

February 28, 2025

    

February 29, 2024

Beginning balance

$

35,580

$

28,270

Additions

2,775

931

Payments received

(350)

(286)

Ending balance

$

38,005

$

28,915

Six Months Ended

February 28, 2025

    

February 29, 2024

Beginning balance

$

40,964

$

24,999

Additions

7,663

4,202

Payments received

(10,622)

(286)

Ending balance

$

38,005

$

28,915

The note receivable from the Sky Ranch CAB accrues interest at 6% per annum. Public improvements which do not qualify for reimbursement at the time of being incurred are considered contract fulfillment costs and are recorded as land development construction costs as incurred. If public improvement costs are deemed qualified for reimbursement, the costs are recognized as notes receivable - related party. The Company assesses the collectability of the note receivable from the Sky Ranch CAB, which includes reimbursable public improvements, project management fees and the related interest income, at each reporting period. The Sky Ranch CAB has an obligation to repay the Company, but the ability of the Sky Ranch CAB to do so before the contractual termination dates is dependent upon the establishment of a tax base or other fee generating activities sufficient to fund reimbursable costs incurred.