Quarterly report pursuant to Section 13 or 15(d)

REIMBURSABLE PUBLIC IMPROVEMENTS AND NOTE RECEIVABLE FROM THE SKY RANCH CAB

v3.22.1
REIMBURSABLE PUBLIC IMPROVEMENTS AND NOTE RECEIVABLE FROM THE SKY RANCH CAB
6 Months Ended
Feb. 28, 2022
REIMBURSABLE PUBLIC IMPROVEMENTS AND NOTE RECEIVABLE FROM THE SKY RANCH CAB  
REIMBURSABLE PUBLIC IMPROVEMENTS AND NOTE RECEIVABLE FROM THE SKY RANCH CAB

NOTE 2 – REIMBURSABLE PUBLIC IMPROVEMENTS AND NOTE RECEIVABLE FROM THE SKY RANCH CAB

The note receivable from the Sky Ranch CAB reports the balances owed by the Sky Ranch CAB to the Company for reimbursable public improvements, project management fees, and interest accrued on the unpaid balances related to the ongoing development of the Sky Ranch master planned community, which is described in greater detail in Note 1 and Note 14 to the 2021 Annual Report. The Company has advanced funds to the Sky Ranch CAB for the cost of public improvements at Sky Ranch which are the ultimate responsibility of the Sky Ranch CAB.  During the second quarter of fiscal 2021, the Company determined that the Sky Ranch CAB would be able to repay the Company for those improvements, along with the project management fees and interest on these expenses. Upon that determination, the Company began recording the reimbursable public improvements as a receivable from the Sky Ranch CAB (as opposed to the costs being initially capitalized as land under development and subsequently expensed as land development construction costs) and began recognizing project management fee revenue and interest income on the entire note receivable from the Sky Ranch CAB. Prior to that date, payment was not deemed to be probable; therefore, the Company capitalized those costs as land under development and subsequently expensed the reimbursable public improvements and did not recognize any project management fees or interest income due to the uncertainty of collectability. During the three and six months ended February 28, 2022, the Company spent $2.7 million and $6.8 million on public improvements which are payable by the Sky Ranch CAB to the Company and added to the note receivable from the Sky Ranch CAB. Additionally, for the three and six months ended February 28, 2022, project management fees owed to the Company of $0.2 million and $0.4 million, and interest income on the outstanding note receivable of $0.5 million and $0.9 million were also added to the note receivable.

Public improvements which are not probable of reimbursement at the time of being incurred are considered contract fulfillment costs and are expensed as land development construction costs as incurred. If public improvement costs are deemed probable of collection, the costs are recognized as notes receivable - related party. The Company assesses the collectability of the note receivable from the Sky Ranch CAB, which includes reimbursable public improvements, project management fees and the related interest income, when events or circumstances indicate the amounts may not be recoverable. The Sky Ranch CAB has an obligation to repay the Company, but the ability of the Sky Ranch CAB to do so before the contractual termination dates is dependent upon the establishment of a tax base or other fee generating activities sufficient to fund reimbursable costs incurred.

The following table summarizes the activity and balances associated with the reimbursable public improvements, project management fees, and accrued interest, all of which are included in the note receivable from the Sky Ranch CAB:

(In thousands)

    

Balances at
August 31, 2021

    

Activity during the six months ended
February 28, 2022

    

Amounts payable by the Sky Ranch CAB at
February 28, 2022

Phase 1

Reimbursable public improvements and other

$

17,645

$

335

$

17,980

Accrued interest

 

2,526

 

676

 

3,202

Project management services

 

1,570

 

16

 

1,586

Phase 1 reimbursable costs

$

21,741

$

1,027

$

22,768

Phase 2

Reimbursable public improvements and other

$

2,935

$

6,498

$

9,433

Accrued interest

33

212

245

Project management services

85

432

517

Phase 2 reimbursable costs

$

3,053

$

7,142

$

10,195

Total reimbursable costs

$

24,794

$

8,169

$

32,963

Total reimbursable costs

$

24,794

$

8,169

$

32,963

Less current portion

16,000

16,000

Non-current reimbursable costs

$

8,794

$

8,169

$

16,963

The note receivable from the Sky Ranch CAB accrues interest at 6% per annum.